Change Order Template: Price, Approve and Bill Every Extra

Updated

A change order being signed on a toolbox lid at a renovation

A change order is a written price for work that isn't on the quote, approved before you do it and billed on the next invoice; one custom home builder we studied found that about $1.4 million of changes done without a real one had made him just $32,000. Skip any of those three steps and the extra work is usually free.

Below: what happens when changes aren't priced, what counts as a change in 8 trades (with prices for the common surprises), how to price one, a clause to copy and a one-page template.

What happens when changes aren't priced or written down

Extra work done without a written price and a markup earns almost nothing, even when the amount of work is large. The builder above did every change a homeowner asked for on a $4.2 million house, barely marked them up, and only checked the numbers at the end. The changes added about $1.4 million and six months, and $32,000 of profit on $1.4 million is about 2.3%. After the extra insurance and site rentals, he thinks they probably lost money.

Here is the same problem on a small job. Say you quote a $4,000 bathroom repaint and the customer asks you to "also do the hallway" while you're there. It takes you 6 hours and $80 of paint. If you never write it down, you bill nothing and the $4,000 job now pays for 6 more hours. If your break-even rate is $50 an hour, that is $380 of cost you ate, before any profit.

What the builder changed once he saw the numbers:

What they changed Before After
Markup on changes Barely any 35 to 45%, more than the house itself (margins in the high teens)
Schedule Not written down Days added written on every change order
Billing At the end On the next draw, typically within a week
Building the change Before payment Only after it's paid
Haggling Negotiated If it's too expensive, skip it and keep building

The same math holds at any size: a $400 extra on a $4,000 job is 10% of the job either way.

Why extras agreed out loud don't get paid

Once the extra work is in the wall, the customer holds all the bargaining power over its price. A contractor who says "we'll settle the price later" and does the work has already given away the one thing that gets a price agreed: the choice not to do it.

The fix is a simple rule: no extra work starts without a written price and a written yes. On commercial jobs, the contract often means an unsigned extra is never owed at all. On a small residential job, the risk looks like this: the customer asks, while the machine or the ladder is already there, for one more small thing. It's never five minutes, and your time and equipment cost money every hour they run.

What counts as a change in 8 trades, with prices

Anything not written in the quote's scope is a change, and the common ones in each trade can be priced before the job starts. Putting that price in your terms means the customer has already seen it when the surprise shows up.

Trade Common change Price or rule Where the number comes from
Roofing Rotten decking after tear-off $85 a sheet installed, photos first Roofing calculator example terms
Roofing Second layer of shingles under the first $65 a square as a written change order Roofing calculator example terms
Painting Extra colours past the number on the contract 1 gallon + 1 hour per extra colour One painting owner's rule
Painting Rot found on an exterior Added about $1,700 on one house One painting estimate we studied
Drywall Walls taller than the plans, vaults A $17,000 price became $26,000 to $27,000 One drywall owner's job
Drywall A reveal nobody priced About $500 per reveal One drywall estimator
Plumbing Seized old valve at the tie-in Up to 3 hours to get it out One plumbing owner
Fencing Rock, old footings or roots in a post hole Charged per hole One fence owner's rule
Pressure washing Moving the customer's patio furniture $100 One pressure washing owner
House cleaning A visit that needs more time $58 per cleaner per hour, approved first One cleaning owner's rate
Lawn care A narrow gate forcing the push mower Plus $5 a visit One lawn care owner

Two of these show why writing the scope down matters. If the painting estimate says three colours, a fourth colour is plainly a change, and nobody has to argue about it. And an old valve at a plumbing tie-in can look like a 20-minute swap until it won't turn; at a $69.95 break-even rate, 3 hours of fighting it is about $210 of cost that a flat price would have swallowed.

How to price a change order

Price the change the same way as the original job, then add for the disruption, because the same work costs more once the job is underway. Don't guess on the spot; send the price within the day.

Line How to price it Where it's explained
Labour Hours x your break-even rate, not the wage True hourly rate guide and free rate calculator
Materials Today's price, small quantities, plus the extra supply run Your price list
Paperwork Writing it up, getting approval, billing: real time Count it like any other hour
Working around finished work The same wiring or trim costs more once walls are closed or paint is on Add hours for the extra care
Profit Your normal markup or more Markup vs margin
Days added Written on the change order The template below

Here is the hallway from earlier, priced properly: 6 hours x $50 = $300 of labour, $80 of paint plus a 25% markup = $100, half an hour of paperwork = $25, total cost $425. Price it for a 25% margin and it is $425 / 0.75 = $566.67, written down and approved before the first coat.

After the job, job costing shows whether the changes actually made money.

Credits for removed work are not the reverse of extras

Removing work costs time too, so a credit is the original line price minus the cost of taking it out, not the full price. Say a light fixture was quoted at under an hour of labour. Once it is already installed, taking it out means shutting off the circuit, removing the fixture, capping the wires, patching the box and updating the paperwork, and that can take several times the hours it was priced at.

If the material is already bought or cut, it isn't credited at all unless you can return it.

A change order clause you can copy

Put one short paragraph in the terms of every quote so the customer agrees to the process before any change comes up. It's plain on purpose, so it gets read. This is sample wording, not legal advice; have a local lawyer check it if your jobs are large.

Changes to the work. This price covers only the work written on this quote. If you ask for anything added or changed, or if we find a hidden problem once work starts (for example rot, rock or old damage), we will stop and give you a written change order with the price and any extra days. We only do that work after you approve it in writing, by signature or by a text or email that says yes to that price. Approved changes are billed on the next invoice. Verbal requests are not included in this price.

Each of our trade calculators writes its own version of this into the customer terms, with that trade's usual surprises named.

A change order template, one page or one text

Eight fields are enough, and a text message with all eight plus a written yes does the job on small residential work.

Field Example
Change order # and date CO-3, June 12
Original quote # Q-2041
What's changing Replace 6 sheets of rotten roof decking found after tear-off
Why Hidden condition, photos sent
Price of this change 6 x $85 = $510
Days added 0
New job total $14,599 + $510 = $15,109
Approved by Name, signature or written yes

The example uses the roofing calculator's 20-square sample job ($14,599) and its example decking price. Keep a running list on each job so that when it ends, every change is already approved and billed. Whether to give a fixed quote or an estimate in the first place is covered in quote vs estimate.

Questions owners ask

What is a change order?

A short written agreement that changes the work after the customer accepted your quote. It says what is added or removed, the price, the days it adds, and it carries the customer's approval before any of that work starts.

What should be included in a change order?

Eight things: a change order number and date, the original quote number, what is changing, why, the price, days added, the new job total and the customer's approval. The template on this page has all eight in one table.

Who pays for a change order?

The customer, when the change is something they asked for or a hidden condition your quote said would be priced separately. If the change fixes your own mistake, such as a wall height you assumed instead of measured, it is usually on you.

Can a change order be approved by text or email?

Often, yes, for small residential jobs, as long as the reply says yes to a stated price. Whether that holds up in a dispute depends on your state and your contract, so have a local lawyer check your wording if the amounts are large.

How much should I mark up a change order?

At least your normal markup. One custom home builder we studied charges 35 to 45% on changes, against margins in the high teens on the house itself, because changes cost office time and disrupt the schedule.

When should I bill a change order?

On the next invoice after it is approved. The same builder invoices each change on the next draw, usually within a week, and does not build it until it is paid.